What to expect this month in Chilcoot paving project
Work is continuing on the $17.4 million Chilcoot pavement rehabilitation, which is scheduled for completion by the end of November.
Project officials anticipate another three to four weeks of paving and guardrail work, followed by shoulder work and striping.
The current schedule is for one-way traffic control at two locations in the project area, Monday–Friday, between 6 a.m. and 10 p.m. daily.
Motorists can anticipate a total of 30-minute delays through the project area. Twenty-four hour traffic control operations are underway and are anticipated to run Sunday through Friday through October.
Traffic control is planned to start each Sunday at 7 p.m. and end each Friday at 6 p.m., with up to 30-minute delays. All construction work and scheduling are weather dependent.
California Highway Patrol units will be on site to assist with any traffic issues. Speed limit reductions remain in place within the project limits.
“We greatly appreciate the public’s patience on this major roadway rehabilitation between Chilcoot and Hallelujah Junction,” said Ronald Collins, Caltrans resident engineer for the project. “The next few weeks will encompass a lot of pivotal work, and we apologize in advance to locals and motorists who regularly utilize this stretch of highway.”