ADDENDUM TWO for PUSD Bid

CRM GROUP

Construction Resource Management

ADDENDUM TWO

February 11, 2022

To Bid Advertisement dated February 3, 2022 and Addendum One dated February 8, 2022

Plumas Unified School District

Building A & B Modernization at Chester Elementary School

BID PACKAGE PU2022.5.24.A Abatement / Demo

Prepared by:   CRM Group
5736 Sumrall Way

Reno, NV 89502

Notice to Bidders

  • Receipt of this Addendum shall be acknowledged on the Bid Form.
  • This Addendum forms part of the Contract documents for the above referenced project and shall be incorporated integrally therewith.
  • Each bidder shall make necessary adjustments and submit his proposal with full knowledge of all modifications, clarifications, and supplemental data included therein. Where provisions of the following supplemental data differ from those of the original Contract Documents, this Addendum shall govern.

General:

Item No. 1            Bid/Contract Documents:

  • The calendar days to complete the project have been changed from 9 to 12, and the completion date has been changed from March 15, 2022, to March 18, 2022.
  • Bid Package PU2022.5.24.A Abatement / Demo is included in this addendum.

Item No. 2            Plans/Specifications/Scope Clarification: The following items shall serve as clarification to the Scope of Work:

  1. Scope Clarification for this bid package is included in this addendum.

END OF ADDENDUM